| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
|---|
| 27 | 28 | 29 | 30 | 1
KEL VANITY COUNTER BED 2 WD FLOOR MSTR BED RAD BRD M BED RADIANT TUBE MOVE LOW DOORS MOVE MAIN DOORS LOW DR HARDWARE MAIN DOOR PREP STEAM VERT MUD FRONT STONE LOUT | 2
SHOWER DOOR START BED 2 WD FLOOR; MSTR BATH TILE LOUT M BED RADIANT BRD BTH & MECH DR KNOBS MAIN DOOR STRIKES MAIN DOORS PREPM BATH FLR TILES LOUT REAR STONE LAYOUT MTR BATH TILE LOUT SAT SEPT26 HRS DAN .5.0 OSCAR 8.0 JASSER 8.0 GABBY 8.0 | 3 WEEK SUMMARYMASTER STEAM PAN MSTR STEAM PAN INSP UPPER RADIANT INSP KEL SHWR GROUT KEL BATH GROUT KEL BATH ALL SEAL KEL VANITY COUNTER SHWR DOORS START STEAM SHWR PAN MUD STEAMSHWR VERTMUD THERMOSTATS MISC M BED RAD BRD M BED RAD TUBE KEL BATH BASE KEL VANITY BASE INT BEAM SCAFFOLD LOW DOORS MOVE MAIN DOORS MOVE LOW DOOR KNOBS TUBKITDRMSOFFITLIGHT LOW DOOR COLOR MAIN DOOR PREP UPPER WOOD FLOOR
|
4 TOWELL BARS NEEDDOOR HARDWARE CAB HARDWARE NEED WEST TREES MTG CLOSET DATE SET
REAR TRENCHING | 5
fire insp solar P, B, SHOWER DOOR SET MSTR WD FLOOR MSTR BED 2XW PREP M CLOSET 2 X 2 PREP STEAM SROCK FINISH MSTR RADBRD FILLER LAUNDRY RAD FILLER LRM1/2RADTUBELOUT MAIN DOORS PREP PANTRY FORM STRIP REAR STEPS FORM STRIP STEAM SHWR ROCK STEAM W SEAL TAPE KEL BATH SEAL KEL SINK GROUT
| 6
MSTR BED WD FLOOR UP DOORS SET UP INT BEAMS START KITCHEN BEAMS GRADE DEER RUN MAIN DOORS PREP REAR FORMS STRIPSTEAM W SEAL 2 SEAL STEAM SHWR 1 KEL SINK SEAL | 7
MSTR BED WD FLOOR MSTR CLOSET WD FLR KEL SHWR DOORS BATH 3 SHWR DOORS KEL TOILET SET KEL SINK PLUMB L RM BEAMS SET UPPER DOOR KNOBS CLOSET DOOR PULLS MAIN DOORS PREP STEAM SHR SEAL 2 STEAM PEBBLE FLR STEAM BENCH SET MSTR CEMENT BRD | 8
MSTR CLOSET WD FLR D RM BEAMS SET MAIN RADIANT MAIN DOORS COLOR STEAM BENCH SET CEMENT BRD MASTER
| 9
ALL BASE READY WD FLOOR MOVE MISC UP STAIR RAIL HEREX5 ENTRY BEAMS SET MAIN RADIANT SLIDERS MISC SEAL MAIN DOORS COLOR STEAM BENCH SEAL STEAM TEMPLATE SAT OCT 3RD HOURS STEAM SHWR D ROCK DAN 5.0 OSCAR 8.0 JASSER 6.5 GABBY 8.0
| 10
WEEK SUMMARY SOLAR FIRE INSP P.B REAR FORMS STRIP BATH 3 SHWR DOORS KEL BTH SHR DOORS MSTR BED WD FLOOR MSTR CLOSET WD FLR WOOD FLOOR MOVE,,, STEAM DENSE ROCK STEAM W SEALX 2 KEL SINK GROUT KEL SINK SEAL KEL BATH SEAL X 2 MAIN RADIANT LOUT KELS TOILET SET KELS SINK PLUMB MSTR TUB DRAIN... MSTR RAD FILLER LAUNDRY RAD FILLER INT BEAMS SET UPPER DOORS SET UPPER DOOR KNOBS UP DOOR PULLS MAIN HARDWARE PREP GRADE MISC DEER RUN MAIN DOORS PREP MAIN DOORS COLOR |
11
LANDSET FINAL INSP | 12
LOW FLR SCRAPE MAIN BASE READY BED 1 WD FLOOR STAIR RAIL PRIME MAIN DOORS COLOR | 13
BED 1 WD FLOOR KIT COUNTER STONE STAIR RAIL PRIME TERRACE STONE | 14
DRIVE PAVING TIE IN LOW HALL WD FLOOR KIT COUNTER STONE STAIR RAIL PAINT TERRACE STONE | 15
COUNTY SOLAR INSP KEL OFFICE WD FLOOR LOW MIRROR SET KIT COUNTER STONE STAIR RAIL PAINT TERRACE STONE | 16
,BALCONY RAIL3 DAYS KEL OFFICE WD FLOOR MAIN HALL WD FLOOR LAUNDRY WD FLOOR STAIR WD FLOOR KIT COUNTER STONESTAIR RAIL INSTALL TERRACE STONE | 17
WEEK SUMMARY FENCE AND GATES |
18 APPLIANCES PREPREAT TERRACE STONE | 19
STAIR RAIL SETTING BED 1 WOOD FLOORKIT STONE MTG REAR TERRACE PLASTER | 20
STAIR RAIL SETTING BED 1 WD FLOOR
| 21
STAIR RAIL SETTING BED 1 WD FLOOR KIT BACKSPLASH | 22
BALCONY RAIL SET LOW HALL WD FLOOR KIT BAR STONE | 23
BALCONY RAIL SET ELEV WD FLOOR KIT BAR STONE | 24 LANDSCAPE VERIFY |
25 FINISH HARDWARE | 26
KEL WOOD FLOOR AV WOOD FLOOR HALL WOOD FLOOR ELEV WOOD FLOOR | 27 KEL WOOD FLOOR | 28 KEL WOOD FLOOR
| 29 THEATER CARPET | 30 THEATER CARPET | 31 FENCE |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |